Georgia Construction, Bond & Lien Law Blog


Georgia’s Notice to Owners–A Primer

Posted in Notices to Owner (NTO's) by Administrator on the June 2nd, 2018

Most southeastern states require suppliers and subcontractors to give some sort of Notice of Furnishing or Notice to Owner (“NTO”); however, each state has its own special requirements and relying on one state’s requirements to get through another state’s requirements will land you in hot water.  We get a number a telephone calls each week from suppliers and materialmen from nearby states who are providing construction materials on Georgia projects, and they ask us about Georgia’s NTO requirements.  Today, we thought you might appreciate a brief overview of Georgia’s NTO requirements.

What is a Notice to Owner (“NTO”)? An NTO is a required notice which lists who is supplying materials or who has been subcontracted on a construction project in Georgia.  The NTO must contain certain information as mandated by the Georgia legislature, and it must be sent to the owner of the construction project as well as the project’s general contractor (this second letter is sometimes referred to as a Notice to General Contractor).

Why are Notices to Owner Required? Generally speaking, project owners are responsible for making sure that the money they pay on construction projects filter down to all the  contractors, sub-contractors and materialmen who worked on the project.  During Atlanta’s construction boom in the 1990’s, construction projects where getting larger and larger, and it was difficult for project owners to track their payments down the line.  Of course, project owners knew whom they had hired as the general contractor, and the general contractor (acting as the project owner’s agent) knew the subcontractors they had hired.  However, identifying the sub-subcontractors and material suppliers was a daunting tasks.  Thus, the Georgia Legislature instituted the NTO construction notice procedure.

Who Must Give a Notice to Owner? Third-tier (and lower) subcontractors and materialmen are required to give NTO’s.  Contractors in a direct contractual relationship with either the project owner or the general contractor do not need to send an NTO; this is referred to as “privity of contract”.   Even though they are not required under Georgia’s statutory notice scheme to send an NTO, we have several clients who work directly for the owner or the GC who send NTO’s in order to “emphasize” that they are on the job and expect prompt payment.

Are There Exceptions to Sending an Notice to Owner (“NTO”)? Yes, third-tier contractors and suppliers are required to send an NTO only if the project owner or the general contractor filed a Notice of Commencement in the real estate records in the county where the project is located.  If such a Notice of Commencement is not filed, then an NTO is not required to be sent.  Similarly, if the Notice of Commencement is invalid or improper, than the sub-subcontractor or supplier’s obligation to send an NTO may be excused.

If a Notice to Owner (“NTO”) is Not Sent, Can a Materialmen’s Lien be Filed? It depends on the specific circumstances.  It can depend on such things as the type of contract used between the parties, the nature of the Notice of Commencement, the work dates, etc., and we encourage you to contact your lawyer or us for an analysis of your unique circumstances.

What Information Must be Included in a Georgia Notice to Owner or Notice to Contractor?  Georgia’s statutory construction notice scheme must be strictly followed; in order to send a proper notice, an NTO must include the following information:

  • The name, address and telephone number of the entity/person providing labor, services, or materials;
  • The name and address of each person at whose instance the labor, services, and materials are being furnished;
  • The name and location of the project as set forth in the Notice of Commencement; and
  • A description of the labor, services or materials being provided and, if known, the contract price or anticipated value of the labor, services or mateials to be provided or the amount claimed to be due, if any.

Notices to Owners, Notices to Contractors, Notices of Furnishing and Notices of Commencements can be very confusing to those new to the industry or those from another state which has similar–but different–requirements.  Therefore, we have put this blog post together for informational purposes only and encourage those with questions to seek competent legal advice (contact us!).  We also ask our fellow practitioners (particularly those in other states) to comment on or link to information related to Notices to Owners in their own states.  Thank you!

7 Responses to 'Georgia’s Notice to Owners–A Primer'

Subscribe to comments with RSS


  1. on March 22nd, 2011 at 9:08 pm

    […] Notice to Owner & Notice to Contractor: Must be given within 30 days of the first day in which you are on the job or begin supplying materials to the jobsite; […]


  2. on November 30th, 2011 at 5:07 pm

    […] out it’s Notice to Owner or Notice to Contractor (hereinafter “NTO”) which, as we know from other blog entries, is essential for all third tier subcontractors and suppliers.  Thus, the owner of the property […]


  3. on April 17th, 2013 at 10:51 pm

    […] you are a third tier supplier or sub-subcontractor, make certain that you send a Georgia Notice to Owner and a Notice to Contractor (sometimes called a Notice of Furnishing) within 30 days of the first day in which you begin work […]


  4. on June 13th, 2013 at 3:09 pm

    […] out it’s Notice to Owner or Notice to Contractor (hereinafter “NTO”) which, as we know from other blog entries, is essential for all third tier subcontractors and suppliers.  Thus, the owner of the property […]


  5. on May 21st, 2014 at 7:02 pm

    […] Assuming that you are statutorily authorized to file a lien, you may (or may not!) have had a condition precedent in order to preserve your right to file a lien.  If your contract is directly with the project owner, there is no requirement that a preliminary notice is required; if your contract is with the prime contractor, then a preliminary notice is not required.  If your contract is with a subcontractor, then you are required to send a Notice to Owner/Notice to General Contractor within the first thirty (30) days that you begin working.  These notices should be sent every time you contract with a subcontractor or supplier as they will PRESERVE your right to file a materialmen’s lien if necessary.  Failure to timely send the preliminary notices may prevent you from having any lien rights (there are always exceptions, however, so please check with your attorney if you were unable to or failed to send a proper notice).  For more information on Georgia’s statutory construction notice scheme, please click here > > […]


  6. on August 19th, 2014 at 9:39 pm

    […] Preliminary Requirements for Filing a Lien in Georgia: Those in privity of contract with either the owner or the general contractor do not have any preliminary notice requirements in Georgia; however, if you are a third tier sub-subcontractor or material supplier then you probably need to send a Notice to Owner and a Notice to Contractor (sometimes called Notice of Furnishing, NTO, or NTC) within the first 30 days you began working on the project.  To learn more about NTOs, please click here > > […]


  7. on August 21st, 2014 at 6:04 pm

    […] are not in privity of contract with either the project owner or the prime contractor must send a Notice to Owner and a Notice to Contractor (“NTO”) in order to preserve the right to file a Payment Bond […]